This three-story brick building on Milwaukee’s east side was
constructed in 1864. Currently, it is home to a professional relocation
company with over 40 employees.
The new three-story, full basement addition would expand the
capacity for office work space by adding 18 more work stations. The
basement would be utilized for file storage.
There were several challenges and concerns presented with this
project:
- It was imperative that the three-story addition match the
architectural personality of the existing structure as best
possible. If this was not achieved the addition would stand out
sorely among the other historical properties.There could be little to no interruption in business during the
construction.
- The project manager had to accommodate, coordinate and
organize many different schedules.
A two-story enclosed airing porch built in 1915 was located on the
property line and had to be removed to make way for the addition.
Due to the age of the building, lead and asbestos testing and
abatement took place. Once that was complete, access to the
main building from the airing porch was blocked off and it was
disassembled by hand. Heavy equipment could not be used to
complete this task due to limited job site space.An existing outside bay
was demolished and the
process of removing
windows and doors began
at the top floor. Three layers of masonry
brick were removed and
multiple microlams were
installed to support each
floor before proceeding to
the next one below. Before tying in the flooring
between the addition and
existing building, the floors
had to be straightened by
jacking up the sagging
areas; up to 3” in some
spots. Existing floors were
then secured to new
microlams. Steel columns and beams were fabricated and erected for
cantilevered balconies with concrete deck surfaces. Pella Smart Sash III windows were sized and positioned to achieve
balance with the existing windows on the original building. This
allowed for ample natural light into the addition. The windows
included in-between-the-glass blinds to control light and privacy. The
units were primed and two-coat finish painted to match the existing
interior. A brick veneer was used to finish the exterior of the addition with
matching Indiana limestone lintels and sills.Taylor stainable steel
exterior doors with
decorative Emtak hardware
were installed on each
floor.
Custom aluminum
brickmolding, similar to the
original building’s profile,
was installed as trim. The interior 15-lite doors
had solid wood jambs, ball
bearing hinges and
matching lever handles.Parabolic lenses were used in
conjunction with the fluorescent
lighting. These lenses are easier
on the eye and provided general
and task lighting. Additional task
lighting was made available
within each cubicle and additional
outlets throughout.
Interior custom profile moldings
were used throughout.Prior to construction, the site had to be prepared by removing trees,
overgrown landscape and a buried water fountain.
The remaining lot space was developed into an era-specific courtyard
that would be used to host several special events throughout the year.
The yard had to include space for seating and gathering.
Significant elevation adjustments were made for a new courtyard
which would include decorative retaining walls. Slight-pitch sidewalk
paths, to comply with ADA requirements, lead to an elevated stamped
concrete courtyard.The decorative
balcony railings had
¼” tempered safety
glass not only to
comply with code but
to also provide a
panoramic view of
the courtyard and
lakefront. Heavy gauge, period-styled aluminum fencing and gates
were to accent the courtyard, protect and secure the perimeter and
offer privacy.A custom made green canvas
rollout awning was installed over
the third floor balcony to offer
protection against the weather.
The color was repeated to match
the exterior doors and new
shutters.The existing building was tuck pointed to match the now new
courtyard and the original front steps were replaced along with the
foundation. The entrance way and the balance of the front elevation
were also refurbished by replacing rotted wood with Azek. Door
hardware was replaced with matching the architectural era of the
building.
The front and courtyard exterior window trim was reconfigured for a
more distinguished look and emphasized with new shutters.This 19th century east side building has plenty of distinguishing character
which was carried through and into the three story addition with the use
era-specific styling. The building/business owner’s wish for an
architecturally accurate finished building was granted.The construction was completed with little to no interruption of business.
Crews worked first and third shift not only to complete the project as
quickly as possible but also to avoid distracting the staff.
Not only did the project manager do an outstanding job of
accommodating, coordinating and organizing dozens of people involved
with this project, he also kept the communication lines between himself
and the building/business owner open.
The building/business owner’s concerns and the onsite
challenges we overcame were numerous, however, the reward of
completing an extensive addition on a building with such historical
attributes was well worth our effort. The owner was also pretty
ecstatic that the project came in under his maximum budget dollar
amount of $1,000,000.